Pitt County Bridge Replacement Project to Begin

As of August 9, 2023 bridge work near the Pitt Greenville Airport may impact driving times.
At peak times, travelling north across the bridge to the airport may take 10-15 minutes longer than expected.

Work to replace a decades old bridge in Greenville is scheduled to begin next week.

A N.C. Department of Transportation contractor is planning to start the replacement of U.S. 13 (Memorial Boulevard) Northbound bridge over the Tar River July 10.

The current bridge, built in 1955, will be replaced with a taller and longer bridge. The project also includes contractors installing a new waterline and improving drainage in the area.

The contractor will begin in mid-July by closing one lane in both the north and southbound lanes to work on the crossovers. Once complete, as early as late summer, traffic will shift into the southbound lanes in a two-lane two-way pattern.

If possible, NCDOT encourages drivers to use an alternate route such as U.S. 264 to N.C. 43 and Stantonsburg Road.

The contractor is expected to open the new bridge to drivers in fall 2025.